Budowa Centrum Nauk Biologiczno-Chemicznych Uniwersytetu Warszawskiego

Construction of University of Warsaw Biological and Chemical Science Centre

Construction of University of Warsaw Biological and Chemical Science Centre - multi-altitude building body with courtyard.

Scope of work:

Construction of technical facilities, specialized laboratories, lecture halls and conference rooms, classrooms, sanitary on each floor, two circulation paths with lifts, laboratory equipment (tables, laboratory worktops) devices and air-conditioning-ventilation systems, electrical, sanitation facilities, fire protection and telecommunication.

Building specifications: volume – 50 069 m3, 5 overground floors, 1 underground floor

Total usable area: 10 456 m2

Investment value: 65 637 453,25 PLN gross

Execution period: 19 months - completion in 2015

Investor: University of Warsaw

General Contractor: Aldesa Construcciones S.A.

 