Construction of Pruszcz Gdański electrical substation r with power line, fibre optic tract and SN15kV.

Scope of work:

Construction of switchboard and cable line 110kV, station building with 15kV switch gear and signal post, 2 transformer 110/15kV, 25 MVA, compensating units, capacitor battery positions, secondary circuits, telemechanic systems, control and supervision systems, cable SN-15kV, fiber optic lines.

Investment value: 33 558 814,10 PLN gross

Execution period : 2012 - 2013

Investor: Energa - Operator S.A.

General Contractor: Aldesa Nowa Energia Sp. z o.o.